京东方C8项目工地视察

BOE C8 Project Construction Site  Supervision

Sept. 2017

钢结构接近完工 / Steel structure almost done

随着设计方案及结构施工图纸的提交,现场结构拆除及钢结构搭建已经紧锣密鼓的展开。随着工期的要求,日前钢结构及屋顶开窗已经基本完工,预期室内装饰及各专业将如期进场。

With the design scheme and construction drawings submitted, the demolition of the site structure and steel structures have been in full swing. With the requirements of the construction period, a few days ago the steel structure and roof windows have been basically completed, the expected interior and other professional will be on schedule.